Grafiku ida ne'e hatudu projetu suku nian bazeia ba kategoria ne'ebé diferente.
Grafiku ida ne'e hatudu persentajen projetu nian bazeia ba progresu ne'ebé mak projetu sira atinze ona.
| No | Projeto | Kategoria | Fatin | Responsavel | Persentazen | Fundus | Gastus | Balansu | Gastus % | OBS | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | PNDS Regular, F-3, S-4, (Kont. & rehab. Estrada Rurais/Sirtu) Sira Lari Tinan 2022 | Estrada | Sira Lari | PNDS |
|
$43.642,94 | $43.599,00 | $43,94 | 99.90% | Finalizado | Finaliza Ona |
| 2 | Pnds Regular, F-3, S-5, (Kont. Moru Escola EBF Bulai-Wesa'). Tinan 2023 Manutensaun 15% $ 6,281.71 Aldeia Sira Lari | Edukasaun | Sira Lari | PNDS |
|
$35.595,86 | $35.532,20 | $63,66 | 99.82% | Finalizado | Finaliza Ona 50% Prepara ba Fali 100% Adicional Sei prossesu ba Manutensaun 15% |
| 3 | Pnds Regular, F-3, S-6, (Kont. & rehab. Estrada Lokal/ Betaun) Lamac-Laran. Tinan 2024 | Estrada | Lamac-LAran | PNDS |
|
$44.500,00 | $9.505,00 | $34.995,00 | 21.36% | Lao Hela | ON GOIN Servisu Lao Hela |
| 4 | UKL/UNP - 2 (Sira-Lari, Mamulac no Mane-Ha't = Uma-9). Tinan 2022 | Uma | Sira-Lari, Mamulac no Mane-Ha't | PNDS |
|
$153.306,00 | $145.306,00 | $8.000,00 | 94.78% | Finalizado | Finaliza Ona |
| 5 | RSS (Cabira-Oan). Tinan 2022 | Sede | Sede Suco Caraubalo | PNDS |
|
$12.000,00 | $12.000,00 | $0,00 | 100.00% | Finalizado | Finaliza Ona |